Structural scope:
Concrete - 1480 m3
Steel structures - 749 tons

Software: Autodesk Revit

Services provided:
Structural design, MEP, BIM, Process design, Instrumentation


CHP plant

The project provides for construction of a building that consists of two fire compartments: a mini-CHP building and an office building attached to it.
The mini-CHP is a one-storey, rectangular facility with dimensions 21.0 x 84.0m, the height to the ridge of the building is 26.12m. The facility forms a steel frame with columnar reinforced concrete foundations. Interfloor slabs are made of reinforced cast-in-situ concrete according to the fixed formwork made of profiled sheet.

The office building is a three-storey building with dimensions 12.0х18.0m. It is implemented in the steel frame with columnar reinforced concrete foundations. Interfloor slabs are also made of reinforced cast-in-situ concrete according to the fixed formwork made of profiled sheet

The building was designed in close cooperation with the team, who develops adjacent design disciplines.
The building is extremely filled with various utility networks, platforms, supports. The use of Revit made it possible to avoid collisions between different parts of the building and various utility networks.
Technical solutions